• How do I acquire a building (development) permit?

    The process involved in acquiring a building permit differs depending on whether the applicant is putting up a temporary or permanent structure.

    The process for each case is outlined below:

    Acquring Permit for Permanent Structures
    1. Applicant must show proof of the title by picking a land report form from the Physical Planning Department of the Sunyani Municipal Assembly and attach two (2) copies of the site plan for a report from either Land Title Registry or Lands Commission.
    2. Applicant must submit four (4) sets of building drawings at the Physical Planning Department.
    3. Application must purchase and fill, appropriately, the development permit form / jacket.
    4. Applicant must pay the required submission fees at the Revenue Office of the Assembly after a favorable land clearance report.
    5. For a three (3) storey – structure and above, applicant must attach a soil test and fire report.
    6. For two storey shops or office and above, applicant must attach a fire permit from the Ghana Fire Service.
    7. For all commercial and industrial properties e.g. warehouses, factories etc. applicants must attach a fire report and environment permit.
    8. For four (4) storey-structure and above, applicant must attach structural analysis.

    Acquring Permit for Temporary Structures
    1. Applicant must show proof of title to land / space
    2. In case of a different owner, owner must give a consent letter of affidavit to be submitted.
    3. Applicant is to submit a temporary structure plan showing position of structure, dimensions and type (i.e. metal container or wooden)

    N.B.
    1. In all cases, whether permanent building or temporary structures, inspections are to be carried out before permits are issued.
    2. In case of any query, applicant will be notified through his or her contact number on the application form.

  • Which areas fall under Sunyani Municipal Assembly?

    The following areas of authority and electoral areas fall under Sunyani Municipal Assembly;

    Abetifi
    Abonsuam
    Ahenboboano
    Airport
    Akokorakwadwo
    Akuoko
    Ankobea
    Antwikrom-Benu Nkwanta
    Asuakwa
    Asufufu/watchman
    Atoase
    Atronie
    Atuahenekrom
    Baakoniaba
    Dominase
    Educational Zone
    Gyaase
    Kotokrom
    Lowcost
    Magazine
    Mireku
    New Dormaa
    New Dormaa East
    Nkrankrom
    Nkwabeng
    Nkwabeng North
    Nwawasua
    Penkwase East
    Penkwase West
    Sunyanitifi
    Tonsuom
    Yawhimakrom
    Yawsae
    Zongo


  • 1

  • Question Form

    Ask a Question using the form below.